All dates can vary pending weather conditions.

1. Brentwood Ln. from Cottonwood Creek to Floyd Rd. (2010 Neighborhood Vitality Bridge Improvement Project for the Greenwood Hills HOA)
  • Project Description: Construction of new road culverts, storm sewer, barrier free ramps, water, water services and other improvements.
  • Traffic Impact: Brentwood will be temporarily closed to traffic until late February. Traffic will be detoured via Floyd Road-Melrose Drive-West Shore Drive.
  • Estimated Completion: Late February
2. Plano Rd. between Lookout Dr. and Renner Rd.
  • Project Description: Removal and replacement of pavement
  • Traffic Impact: Both directions on Plano Road between Lookout Drive and Renner Road could be temporarily closed to traffic as needed, mainly from 9:00 AM to 3:30 PM. Two lanes will be available at peak hours.
  • Estimated Completion: Late February
3. Renner Rd. east of Plano Rd.
  • Project Description: Construction of deceleration lane, inlet relocation and drive approaches.
  • Traffic Impact: Different sections of the outside westbound and the outside lanes of Renner Road from Plano Road to Foxboro Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM and at times overnight, if needed.
  • Estimated Completion: Early February
4. Bridge Enhancements Projects – Reservation and Greenwood HOA’s (Mimosa Dr., Melrose Dr., and Campbell Rd.)
  • Project Description: Replacement of metal bridge rails, addition of stone columns with decorative cast stone caps and some sidewalk replacement.
  • Traffic Impact: Traffic lanes next to curbs in the work zones could be temporarily closed to traffic as needed from 9:00 AM to 3:30 PM
  • Estimated Completion: The work along Mimosa Drive and Melrose Drive is planned to start in late September and should be completed by late February. Work along Campbell Road is scheduled to start in mid-October with an April completion date.
5. Greenville Ave. and Alma Rd.
  • Project Description: Utility work
  • Traffic Impact: The outside lane of Greenville Avenue from Campbell Road to Alma Road and the northbound lane of Alma Road just south of Greenville Avenue could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
6. Campbell Rd. at Lakeside Blvd.
  • Project Description: Cable Installation
  • Traffic Impact: The outside eastbound lane of Campbell Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early February
7. Plano Rd. – Columbia Dr.
  • Project Description: Cable Installation
  • Traffic Impact: The south side lane of Columbia Drive and the outside lane of N. Plano Road could be closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
8. Dogwood Dr. – Holly Dr.
  • Project Description: Cable Installation
  • Traffic Impact: The west side lane of Dogwood Drive and the north side lane of Holly Drive could be closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
9. 498 W. Renner Rd.
  • Project Description: Cable Installation
  • Traffic Impact: The outside lane of W. Renner Road could be closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
10. Sherman St. – Main St. – Custer Rd. – Arapaho Rd.
  • Project Description: Cable Installation
  • Traffic Impact: The east side lane of Sherman Street at Polk Street, the the north side lane of Main Street west of Interurban; the west side lane of Custer Road at Westwood Drive and the outside eastbound lane of Arapaho Road, west of Hampshire Lane could be closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
11. Plano Rd. at Arapaho Rd.
  • Project Description: Fiber optic installation
  • Traffic Impact: The southbound right turn of Plano Road lane at Arapaho Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid March
12. Breckinridge Blvd. – Greenfield Dr. – Holford Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of eastbound Breckinridge Blvd. at Loxley Ln., southbound lane of Greenfield Dr. south of Compton Dr. and the southbound lane of Holford Dr. south of Greenfield Dr. could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
13. Glenville Dr. between Galatyn Pkwy. and Waterwood Dr.
  • Project Description: Utility work
  • Traffic Impact: The southbound lanes of Glenville Dr. between Galatyn Pkwy. and Waterwood Dr., as well as Galatyn Pkwy. between Performance Dr. and Glenville Dr. will be closed in phase 1. The northbound lanes of Glenville between Galatyn Parkway and Waterwood Drive, will be closed in phase 2.
  • Estimated Completion: Mid February
14. Coit Rd. north of Campbell Rd.
  • Project Description: Concrete replacement/rehab
  • Traffic Impact: Work will generally include concrete pavement removal and replacement, sidewalk/ leadwalk replacement, 6” concrete curbs, barrier free ramps, sodding and other miscellaneous work. Up to two lanes could be temporarily closed as needed while work is ongoing, but at least one lane will be available during peak times. As needed, some affected lanes will need to stay closed overnight for concrete curing. (part of 2015 Annual Requirements Contract for Street Rehabilitation)
  • Estimated Completion: Late April
15. Jupiter Rd. between Lookout Dr. & Renner Rd.
  • Project Description: New pole installation
  • Traffic Impact: The outside lane of northbound Jupiter Rd., between Lookout Dr. and Renner Rd. could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid April
16. Belt Line Rd. at Cottonwood Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside eastbound lane of Belt Line Road could be closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
17. Renner Rd. west of Plano Rd.
  • Project Description: Street light relocation
  • Traffic Impact: The inside lane of both east and westbound Renner Road, between Routh Creek and Plano Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
18. Palisades Creek Dr. west of US 75
  • Project Description: Street light relocation
  • Traffic Impact: The eastbound lane of Palisades Creek west of US75 could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid April
19. Plano Rd. north of Buckingham Rd.
  • Project Description: Cable installation
  • Traffic Impact: The outside northbound lane of Plano Road north of Buckingham Road could be closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
20. Renner Rd. west of North Star Rd.
  • Project Description: Construction of deceleration lane
  • Traffic Impact: The outside eastbound lane of Renner Road west of North Star Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early February
21. Collins Blvd. at Glenville Dr.
  • Project Description: Fiber optic installation
  • Traffic Impact: The outside eastbound lane of Collins Boulevard west of Glenville Drive and the northbound outside lane of Glenville Drive north of Collins Boulevard could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
22. Renner Rd. west of Alma Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of both directions of Renner Road just west of Alma could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid February
23. Campbell Rd. at of Greenville Ave.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of Campbell at Greenville Avenue could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
24. Shiloh Rd. south of Renner Rd.
  • Project Description: Cable installation
  • Traffic Impact: The southbound outside lane of Shiloh Road between Renner Road and Breckinridge Boulevard could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
25. Arapaho Rd / E. Executive Dr.
  • Project Description: Cable installation
  • Traffic Impact: The westbound outside lane of Arapaho Road at Executive Drive as well as the northbound E. Executive Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
26. Jupiter Rd. north of Buckingham Rd.
  • Project Description: Remove and replace approach
  • Traffic Impact: The outside southbound lane of Jupiter Road could be temporarily closed for traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early February
27. Cityline Dr. east of Plano Rd.
  • Project Description: Construction of turning lanes
  • Traffic Impact: The inside lane of both directions of Cityline Dr. east of Plano Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
28. Belt Line Rd. at Inge Dr.
  • Project Description: Sidewalk replacement
  • Traffic Impact: The outside eastbound lane could be temporarily closed for traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
29. Shenandoah Pl. – N. Waterview Dr. – Laurel Ln. – St. Lukes Dr.
  • Project Description: Street and alley paving, drainage, and utility rehabilitation
  • Traffic Impact: This project includes several alley reconstructions, sanitary sewer, drainage as well as a storm sewer extension. The northbound lane of N. Waterview Drive between Shenandoah Place and Laurel Lane could be temporarily closed to traffic from 9:00 AM to 3:30 PM. The work along Waterview Drive should be completed by mid-March.
  • Estimated Completion: Early July
30. Plano Rd. at Campbell Rd.
  • Project Description: New pole installation
  • Traffic Impact: The northbound right-turn lane of Plano Road at Campbell Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
31. Owens Blvd. at Broadmoor Dr.
  • Project Description: Pole replacement
  • Traffic Impact: The southbound lane of Owens Boulevard at Broadmoor Drive could be temporarily narrowed from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late February
32. US 75 Frontage Rd south of Monte Blaine Ln.
  • Project Description: Gas lane relocation, drive approaches
  • Traffic Impact: The outside southbound lane could be temporarily closed for traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early March
33. Plano Rd. – Arapaho Rd. – Dorothy Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of northbound Plano Road south of Arapaho Road; the outside lane of westbound Arapaho Road as well as the northbound lane of Dorothy Drive south of Arapaho Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid March
34. Waterview Pkwy. – Campbell Rd. – PGBT
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of northbound Watreview, between Campbell and PGBT, as well as the eastbound outside lane of Synergy Park Boulevard, west of Rutford; and the northbound lane of Stewart St could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid March
Links

Interactive Traffic
Information Map

TxDOT Progress Reports

Contact Us

Traffic Management Center
(Signs, Markings,
and Traffic Signals)
972-744-4330
Mon-Fri 6:00-6:00

Traffic and Transportation
Engineering & Planning

411 W. Arapaho Rd., Suite 204
972-744-4320
972-744-5804 (Fax)
Mon-Fri 8:00-5:00

Last updated: 2/9/2016 3:20:16 PM