All dates can vary pending weather conditions.

1. Plano Rd. between Lookout Dr. and Renner Rd.
  • Project Description: Removal and replacement of pavement
  • Traffic Impact: Both directions on Plano Road between Lookout Drive and Renner Road could be temporarily closed to traffic as needed, mainly from 9:00 AM to 3:30 PM. Two lanes will be available at peak hours.
  • Estimated Completion: Late April
2. Renner Rd. east of Plano Rd.
  • Project Description: Construction of deceleration lane, inlet relocation and drive approaches.
  • Traffic Impact: Different sections of the outside westbound and the outside lanes of Renner Road from Plano Road to Foxboro Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM and at times overnight, if needed.
  • Estimated Completion: Early May
3. Campbell Rd. between N. Waterview Dr. and Floyd Rd.
  • Project Description: Bridge enhancements and screening wall extension
  • Traffic Impact: Work includes replacing the metal bridge rails with decorative painted metal railings, adding stone columns with decorative cast stone caps and stone plaques to finish the end columns, and replacing some sidewalks. The Greenwood Hills HOA work will include extending the brick screening wall along the south side of Campbell Road between Waterview Drive and N. Floyd Road. Bridge enhancements on both sides of Campbell Road west of N. Floyd Road and west of Waterview Drive are also included in this project. The outside lane along one side of Campbell Road will be closed at times, as needed, from 9:00 AM to 3:30 PM for construction.
  • Estimated Completion: Mid May
4. Greenville Ave. & Alma Rd.
  • Project Description: Utility work
  • Traffic Impact: The outside lane of Greenville Avenue from Campbell Road to Alma Road and the northbound lane of Alma Road just south of Greenville Avenue could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
5. Plano Rd. at Arapaho Rd.
  • Project Description: Fiber optic installation
  • Traffic Impact: The southbound right turn of Plano Road lane at Arapaho Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
6. Breckinridge Blvd. – Greenfield Dr. – Holford Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of eastbound Breckinridge Blvd. at Loxley Ln., southbound lane of Greenfield Dr. south of Compton Dr. and the southbound lane of Holford Dr. south of Greenfield Dr. could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late April
7. Jupiter Rd. between Lookout Dr. & Renner Rd.
  • Project Description: New pole installation
  • Traffic Impact: The outside lane of northbound Jupiter Rd., between Lookout Dr. and Renner Rd. could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late May
8. Renner Rd. west of Alma Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of both directions of Renner Road just west of Alma could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
9. Shiloh Rd. south of Renner Rd.
  • Project Description: Cable installation
  • Traffic Impact: The southbound outside lane of Shiloh Road between Renner Road and Breckinridge Boulevard could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
10. Cherrywood Dr. at Cottonwood Rd.
  • Project Description: Leak repair
  • Traffic Impact: the north side lane just west of Cottonwood Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
11. Cityline Dr. east of Plano Rd.
  • Project Description: Construction of turning lanes
  • Traffic Impact: The inside lane of both directions of Cityline Dr. east of Plano Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
12. Shenandoah Pl. – N. Waterview Dr. – Laurel Ln. – St. Lukes Dr.
  • Project Description: Street and alley paving, drainage, and utility rehabilitation
  • Traffic Impact: This project includes several alley reconstructions, sanitary sewer, drainage as well as a storm sewer extension. The northbound lane of N. Waterview Drive between Shenandoah Place and Laurel Lane could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early July
13. Plano Rd. at Campbell Rd.
  • Project Description: New pole installation
  • Traffic Impact: The northbound right-turn lane of Plano Road at Campbell Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
14. Owens Blvd. at Broadmoor Dr.
  • Project Description: Pole replacement
  • Traffic Impact: The southbound lane of Owens Boulevard at Broadmoor Drive could be temporarily narrowed from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
15. US75 frontage road south of Monte Blaine Ln.
  • Project Description: Gas line relocation, drive approaches
  • Traffic Impact: The outside southbound lane could be temporarily closed for traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late May
16. Plano Rd. – Arapaho Rd. – Dorothy Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of northbound Plano Road south of Arapaho Road; the outside lane of westbound Arapaho Road as well as the northbound lane of Dorothy Drive south of Arapaho Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
17. Waterview Pkwy. – Synergy Park Blvd. – Stewart St.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of northbound Waterview Parkway, between Campbell Road and PGBT, as well as the eastbound outside lane of Synergy Park Boulevard, west of Rutford; and the northbound lane of Stewart Street could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late May 
18. Spring Valley Rd. east of US75
  • Project Description: Sidewalk removal and replacement
  • Traffic Impact: The outside eastbound lane could be temporarily closed to traffic from 9:00 AM to 3:30 PM. 
  • Estimated Completion: Early May
19. Spring Valley Rd. between Maham Rd. & Waterfall Way
  • Project Description: Gas Line Relocation
  • Traffic Impact: The outside westbound and eastbound lanes of Spring Valley Road from Maham Road to Weatherred Drive could be closed to traffic from 9:00 AM to 3:30 PM. 
  • Estimated Completion: Early May
20. Spring Valley Rd., east of Waterfall Way / Maham Rd., south of Spring Valley Rd.
  • Project Description: Installation of manholes and ducts
  • Traffic Impact: The outside eastbound lane of Spring Valley Road east of Waterfall Way and the outside northbound lane of Maham Road south of Spring Valley Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
21. Custer Road between Hanbee St. and Marilu St.
  • Project Description: Street and alley paving, drainage, and utility rehabilitation
  • Traffic Impact: This project includes several alley reconstructions. The inside northbound lane of Custer Parkway between Hanbee Street and Marilu Street could be temporarily closed to traffic from 9:00 AM to 3:30 PM or overnight as needed for concrete curing (Part of 2010 Alley Rehabilitation Project). 
  • Estimated Completion: Mid May
22. Renner Rd. at PGBT
  • Project Description: Fiber optic installation
  • Traffic Impact: The inside left-turn lane of both directions of Renner Road at President George Bush Highway could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
23. Arapaho Rd. – Glenville Dr. – Commerce Dr.
  • Project Description: Concrete removal and replacement
  • Traffic Impact: The outside westbound lane of Arapaho Road at Glenville Drive as well as the outside southbound lane of Glenville Drive at Commerce Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM or overnight as needed.
  • Estimated Completion: Early May
24. Drive A at UTD
  • Project Description: Roadway improvements, new utilities and road widening
  • Traffic Impact: Drive A will be closed to traffic.
  • Estimated Completion: Late May
25. Spring Valley Rd. from Maham Rd. to west of St. Paul Dr.
  • Project Description: Installation of new aerial cable, removal of old cable
  • Traffic Impact: The outside eastbound lane of Spring Valley Road between Mahan Road and west of St Paul could be temporarily closed to traffic from 9:00 AM to 3:30 PM or overnight as needed.
  • Estimated Completion: Early May
26. Security Row between Bowser Rd. and Integrity Dr.
  • Project Description: Water and sewer lanes installation
  • Traffic Impact: The north side lane will be closed in phase 1 and the south side lane in phase 2 could be temporarily closed to traffic from 9:00 AM to 3:30 PM or overnight as needed.
  • Estimated Completion: Late May
27. Palisades Creek Dr. west of US 75
  • Project Description: Storm sewer connection
  • Traffic Impact: Palisades Creek Dr, between US75 and east of N Collins Boulevard will be temporarily closed to traffic.
  • Estimated Completion: Early May
28. Alma Rd. at Collins Blvd.
  • Project Description: Replacing damaged pull box
  • Traffic Impact: The westbound lane of Alma Road at N Collins Boulevard could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late June
29. Phillips St. east of US 75
  • Project Description: Cable installation
  • Traffic Impact: The eastbound lane of Phillips Street, east of US75 could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
30. Sherman St. south of Kaufman St.
  • Project Description: Cable installation
  • Traffic Impact: The southbound lane of Sherman Street south of Kaufman Street could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
31. Plano Rd. – Renner Rd. – CityLine Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside northbound lane of Plano Road from Broadmore Drive to CityLine Drive, the right turning lane of Renner Road at Plano Road and the eastbound right lane of CityLine Drive just east of Plano Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
32. Spectrum Dr.
  • Project Description: Cable installation
  • Traffic Impact: The southbound lane of Spectrum Drive south of Matrix Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
33. Industrial Dr.-Alpha Dr.-International Pkwy.-Arapaho Rd.-Glenville Dr.-Presidential Dr.
  • Project Description: Cable installation
  • Traffic Impact: The northbound lane of Industrial Drive, the eastbound lane of Alpha Drive, northbound of International Parkway, eastbound outside lane of Arapaho Road the southbound outside lane of Glenville Drive and the northbound lane of Presidential Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
34. N. Collins Blvd south of Fall Creek Dr.
  • Project Description: Cable installation
  • Traffic Impact: The southbound outside lane of North Collins Boulevard south of Fall Creek Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
35. Arapaho Rd. at Yale Blvd and Grant Dr.
  • Project Description: Erosion Control Project
  • Traffic Impact: The outside lane of westbound Arapaho Road from Grant Drive to east of Yale Boulevard could be temporarily closed to traffic from 9:00 AM to 3:30 PM or overnight as needed.
  • Estimated Completion: Late May
36. US75 Frontage Rd. south of Kaufman St.
  • Project Description: Drive approach removal and replacement
  • Traffic Impact: The outside northbound lane of the US75 Frontage Road south of Kaufman Street could be temporarily closed to traffic from 9:00 AM to 3:30.
  • Estimated Completion: Mid May
37. Performance Dr. between Galatyn Pwky & Waterwood Dr.
  • Project Description: New pole installation
  • Traffic Impact: The outside lane of southbound Performance Drive, between Galatyn Parkway and Waterwood Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
38. Campbell Rd. – Waterview Dr. – Floyd Rd. – Laguna Dr. – Fall Creek Dr. – Dumont Dr.
  • Project Description: Test station installations
  • Traffic Impact: The outside eastbound lane of Campbell Road west of Waterview Drive, the outside southbound lane of Waterview Drive at Campbell Road, the outside lane of northbound S. Floyd Road, the southbound lane of Laguna Drive, just east of Dumont Drive, the eastbound lane of Fall Creek Drive east of Custer Parkway and the westbound lane of Dumonth Drive west of Dublin Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late May
39. Executive Dr. W.
  • Project Description: Cable installation
  • Traffic Impact: The east side lane of Executive Drive W could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
40. Collins Blvd. – Firman Dr.
  • Project Description: Cable installation
  • Traffic Impact: The eastbound outside lane of E. Collins Boulevard and the south side lane of Firman Drive, at E. Collins Boulevard could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
41. Campbell Rd. – Lakeside Blvd. – Glenville Dr.
  • Project Description: Cable installation
  • Traffic Impact: The eastbound outside lane of Campbell Road at Greenville Avenue, the southbound lane of Lakeside Boulevard at Lawnview Drive and the westbound outside lane of Glenville Drive east of the US75 could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid May
42. Custer Rd. at Tyler St.
  • Project Description: Cable installation
  • Traffic Impact: The southbound lane of Custer Road and the eastbound lane of Tyler Street could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
43. US75 Frontage Rd. south of Campbell Rd.
  • Project Description: Cable installation
  • Traffic Impact: The southbound outside lane of US75 Frontage Road south of Campbell Road could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
44. Buckingham Rd. west of Sherman St.
  • Project Description: Cable installation
  • Traffic Impact: The westbound outside lane of W. Buckingham Road west of Sherman Street could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
45. St. Paul Dr. – Spring Valley Rd.
  • Project Description: Cable installation
  • Traffic Impact: The southbound lane of Saint Paul Drive and the westbound outside lane of Spring Valley Road, from Saint Paul Drive to west of S. Weatherred Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early May
46. Custer Rd. south of Greenleaf Dr.
  • Project Description: Water line connection
  • Traffic Impact: The southbound lane of Custer Road south of Greenleaf Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM or overnight as needed for concrete curing.
  • Estimated Completion: Early May
47. Melrose Dr. between West Shore Dr. and Wisteria Way
  • Project Description: Utility work
  • Traffic Impact: Minor work to be done in this area. The south side lane of Melrose Drive between West Shore Drive and Wisteria Way could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late July
48. Coit Rd. between Spring Valley Rd. and Belt Line Rd.
  • Project Description: Concrete replacement/rehab
  • Traffic Impact: Work will generally include concrete pavement removal and replacement, sidewalk/ leadwalk replacement, 6” concrete curbs, barrier free ramps, sodding and other miscellaneous work. Up to two lanes could be temporarily closed as needed while work is ongoing, but only one lane will be closed during peak times. As needed, some affected lanes will need to stay closed overnight for concrete curing.
  • Estimated Completion: Late June
49. Synergy Park Blvd.
  • Project Description: New gas service
  • Traffic Impact: The westbound outside lane of Synergy Park Boulevard west of Rutford Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late May
50. Spring Valley Rd. east of Waterview Dr.
  • Project Description: Primary lines location
  • Traffic Impact: The westbound outside lane of Spring Valley Road east of Waterview Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early June
51. Greenville Ave. north of Walnut St.
  • Project Description: Street lights relocation
  • Traffic Impact: The northbound inside lane of Greenville Avenue north of Walnut Street could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early June
52. Melrose Dr. east of Richardson Dr.
  • Project Description: Underground wire replacement
  • Traffic Impact: The eastbound outside lane of Melrose Drive east of Richardson Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late June
53. Columbia Dr. east of Glenville Dr.
  • Project Description: Cable installation
  • Traffic Impact: The outside lane of Columbia Drive just east of Glenville Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late May
54. Palisades Creek Dr. east of N. Collins Blvd.
  • Project Description: New pole installation
  • Traffic Impact: The eastbound lane of Palisades Creek Drive east of N. Collins Boulevard could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early July
55. Arapaho Rd. east of International Pkwy.
  • Project Description: Cable installation
  • Traffic Impact: The outside westbound lane of Arapaho Road east of International Parkway could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Early June
56. Greenville Ave. south of Terrace Dr.
  • Project Description: Cable installation
  • Traffic Impact: The southbound outside lane of N. Greenville Avenue just south of Terrace Drive could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late June
57. Executive Dr. West
  • Project Description: Cable installation
  • Traffic Impact: The southbound lane of Executive Drive West could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid July
58. Greenville Ave. north of Walnut St.
  • Project Description: Construction of turning lanes and drive approach
  • Traffic Impact: The outside northbound lane in phase 2 and the two inside lanes of Greenville Avenue in phase 1, just north of Walnut Street could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Mid June
59. Abrams Rd at Tall Oaks Ln.
  • Project Description: Construction of drive approaches
  • Traffic Impact: The outside lane of southbound Abrams Road just north of Tall Oaks Lane could be temporarily closed to traffic from 9:00 AM to 3:30 PM.
  • Estimated Completion: Late June
Links

Interactive Traffic
Information Map

TxDOT Progress Reports

Contact Us

Traffic Management Center
(Signs, Markings,
and Traffic Signals)
972-744-4330
Mon-Fri 6:00-6:00