Home MenuCuster Parkway Improvement Project
Custer Parkway from Campbell to SH 190
Project Documents |
Oct. 9, 2024 Open House Exhibits |
Stay Connected on Updates - Sign Up for News Alerts HERE |
News
-
Work Expected to Begin Next Week on Custer Parkway Improvement Project
The reconstruction of Custer Parkway from Campbell Road to the President George Bush Turnpike is expected to begin next week.
11/05/2024 4:17 PM
Project Updates:
-
The City of Richardson has awarded a contract to DDM Construction to reconstruct Custer Parkway from Campbell Rd to SH-190. Construction is being performed in three segments, with the waterline, sanitary sewer, and storm drain installations taking place first, followed by pavement replacements. Segment 1 is from Campbell Road to Canyon Creek Drive; Segment 2 is from Canyon Creek Drive to Lookout Drive and Segment 3 is from Lookout Drive to Renner Road.
-
Construction on Segment 1 will begin Nov. 11, or shortly thereafter, and construction on Segment 2 will begin on or after Nov. 18.
-
To allow for enough construction space for the waterline installation, all traffic will be shifted to the southbound lanes (the west side of the roadway) with one lane open in each direction from Campbell to the railroad crossing. Traffic will be shifted to the northbound lanes (the east side of the roadway) from the railroad crossing to Lookout Drive. Additionally, the bike lanes will be closed and on-street parking will be prohibited within the two segments under construction.
-
Trash and recyclable service will continue along the alley and should not be impacted. We will notify you when alley closures are expected.
Project Description:
This project is partially funded by the 2021 Bond Program and will help improve the existing road and utility infrastructure along Custer Parkway from Campbell to SH190.
The project elements included in the project are:
Between Campbell to Renner—
- The street will be fully reconstructed from Campbell to Renner.
- Replacement of the aging water and sanitary sewer system throughout the corridor and some additional storm sewer infrastructure near Fall Creek Drive.
- Sidewalk in this section will only be replaced as needed to facilitate the street and utility reconstruction and where the sidewalk is broken.
- The existing street lighting will be replaced with new LED lighting with underground electrical conduit between the street lights.
- New traffic signals will be installed at Custer and Campbell and Custer and Renner.
Between Renner to SH190—
- This section will have concrete panel replacements as needed where the concrete has failed.
- This section will not be full reconstruction and no utility replacements are planned.
Proposed Typical Section:
The proposed typical road section will match the existing typical section and will include on-street parking, striped bike lanes and one travel lane in each direction.
Project Schedule:
This project is expected to start construction in Fall 2024 and is projected to take 2 years to complete, weather permitting. This schedule is also highly dependent on franchise utility coordination and it is not unusual for that effort to delay a project.
Landscape Impacts:
The project corridor has some existing landscape and has a great aesthetic feel created by trees and median landscape. We are committed to preserving as much of the existing landscape as we can by utilizing enhanced construction methods to help reduce the risk of removal. These enhanced methods will cause construction time to increase as it does slow down the contractor’s production rate and it does increase the costs, but we think it is worth it to preserve the aesthetic feel. Some of the strategies we will employ are:
- Consideration of utility trenches with regards to existing trees. Where practical we have shifted utilities to minimize impact.
- Include contract specifications that the contractor must adhere to including root pruning, tree protection around base of tree, and canopy pruning prior to construction to minimize damage from tall equipment.
- Allow for alternative construction methods when in close proximity to trees including pipe bursting and reduced excavation behind back of curb.
However, we know we will not be able to save every tree and landscape area. Should landscape and trees have to be removed, the following remediation efforts will be taken:
- If in parkway (area between curb and sidewalk) the homeowner will be contacted by the City and worked with to provide compensation for them to replace the tree in an alternative location on their property.
- If in median, the City will replace the tree from an approved species list that is being developed.
- The City is committed to planting additional trees nearby in Custer and Canyon Creek Parks.
For medians with existing landscape areas, the median restoration approach shown in the figure below will be followed:
Additional Questions?
If you have questions regarding this project, please email CusterPhase2@cor.gov and a City Staff member on the project team will respond.
Sign-up below for email distribution list to get updates on this project. Project updates will be sent closer to the start of construction and will continue through construction.